Pool Permit Processing Time: Days From Application to Issue in 12 US Cities, 2019 to 2026

An original count of calendar days between application and issuance for 35,931 new residential in-ground pool permits in 12 US cities and counties, 2019 to August 2026.
Pool Permit Processing Time: Days From Application to Issue in 12 US Cities, 2019 to 2026
The answer

Pool permit processing time in 12 US cities and counties ran from a median of 1 day (San Antonio) to 70 days (Austin) between application and issuance in 2025, by PC&S analysis of municipal permit records. In eight cities tracked since 2019, the typical median more than doubled, from 17 days in 2019 to 38.5 days in 2025.

38.5 days
Median of eight city medians, application to pool permit issue, 2025 (17 days in 2019), eight US cities
70 days
Median days to issue a new residential pool permit in Austin, Texas, 2025, the longest of 12 jurisdictions
37.7%
Share of pool permits issued within 30 days, median across eight US cities, 2025 (71.3% in 2019)
6 of 11
US jurisdictions issuing pool permits faster in January to August 2026 than in the same months of 2025

How we built the dataset

  1. Took the permit universe of the PC&S pool construction statistics report: new residential in-ground pool permits, filtered by permit type and description and deduplicated by address within 365 days.
  2. Kept the 12 jurisdictions that publish both an application date and an issue date; dropped Las Vegas (issue date only) and Fort Worth (filing date only).
  3. Re-pulled Los Angeles (to add submitted_date), Orlando (processed_date) and San Diego (PROJECT_CREATE_DATE) on 2026-10-05; reused the other extracts pulled 2026-10-03.
  4. Converted ArcGIS timestamps to local calendar dates and computed calendar days from application to issue for each permit.
  5. Excluded durations below 0 or above 730 days and records without an application date (472 of 36,403).
  6. Grouped permits by year of issue; computed median, 75th and 90th percentile, share within 30 days and share same day.
  7. Compared January to August 2026 with January to August 2025 by issue month; built the month-of-application index from applications filed 2019 to 2023.
  8. Read state statutes and city guidance pages for published deadlines and process notes.

Included: Permits for new residential in-ground pools issued 2019 to August 2026 within each jurisdiction’s coverage years (San Antonio from 2021, Nashville from 2024, Cape Coral from 2025, East Baton Rouge Parish to 2024).

Excluded: Above-ground pools, spa-only work, remodels, demolitions, supplements and duplicates (sibling-report rules); durations below 0 or above 730 days; records without an application date; Las Vegas and Fort Worth (no date pair).

Conflicting numbers: Where a city publishes more than one possible start date (San Diego project creation vs approval creation), we used the earliest one that a city definition ties to the submission. Published targets are reported beside observed times, not reconciled with them.

Derived metrics: All statistics are computed by scripts/analyze.py from raw/processed/permit_durations.csv; derived.csv lists each formula with its fact-row inputs.

Caveats

  • Application date definitions differ by city; Orlando and Cape Coral publish no definition for their fields.
  • Our clock includes time the applicant takes to answer corrections and pay fees, so it is longer than staff review time.
  • Issued-only files cannot show withdrawn or still-pending applications.
  • Several cities have small annual counts (Raleigh, Montgomery County and New Orleans under 300 a year), so single-year medians move more.
  • Business-day figures exclude weekends but not public holidays.
  • Recorded fee fields are not defined by the cities and may not include every fee.

Method last reviewed October 5, 2026.

The short version

  • In 2025, the median new residential pool permit took 70 days from application to issue in Austin, 67 in San Diego, 61 in Los Angeles and 59 in Cape Coral (City of Austin, City of San Diego, LADBS, City of Cape Coral).
  • San Antonio issued its median pool permit 1 day after application in 2025, and 38.7% the same day (City of San Antonio).
  • Across eight cities tracked since 2019, the median of city medians rose from 17 days in 2019 to a high of 52.8 days in 2023 and stood at 38.5 days in 2025 (PC&S analysis of city permit records).
  • The share of pool permits issued within 30 days fell from 71.3% in 2019 to 37.7% in 2025, using the median across the same eight cities (PC&S analysis).
  • Same-day pool permits disappeared in Los Angeles and San Diego in 2020: the same-day share fell from 32.2% to 0.0% in Los Angeles and from 29.2% to 0.0% in San Diego between Q1 and Q4 2020 (LADBS, City of San Diego).
  • Applications filed in December took 17% longer than a typical month to be issued, measured as an index of 117 across eight cities for applications filed 2019 to 2023 (PC&S analysis).
  • From January to August 2026, 6 of 11 jurisdictions issued pool permits faster than in the same months of 2025, led by New Orleans (38 to 19 days); San Diego slowed most (75 to 88 days) (PC&S analysis).

What the permit data shows

  1. Austin, Texas had the longest median pool permit processing time of 12 jurisdictions in 2025 at 70 days, with 10% of permits taking 275 days or more (City of Austin).
  2. Mesa, Arizona issued 88.4% of new pool permits within 30 days of application in 2025, with a median of 18 days (City of Mesa).
  3. San Antonio, Texas had a median of 1 day from application to pool permit issue in 2025, and 98.3% of permits were issued within 30 days (City of San Antonio).
  4. In 2025, 7 of 12 jurisdictions had a latest-full-year median of 35 days or less, and 4 of 12 (Austin, San Diego, Los Angeles and Cape Coral) were above 55 days (PC&S analysis).
  5. All 8 cities tracked since 2019 had a longer median processing time in 2021 than in 2019; 6 of 8 were faster in 2025 than in 2021, yet 7 of 8 were still slower in 2025 than in 2019 (PC&S analysis).
  6. San Diego, California pool permits went from a median of 1 day in 2019 to 114 days in 2022 and 67 days in 2025 (City of San Diego).
  7. Los Angeles pool permits went from a median of 12 days in 2019 to 79 days in 2023 and 61 days in 2025 (LADBS).
  8. In Los Angeles, the median pool permit issued in Q1 2020 took 6 days; by Q4 2020 it took 64 days (LADBS).
  9. Raleigh, North Carolina pool permit volume rose 195.6% from 2019 to 2021 while its median processing time rose only 3 days, from 29 to 32 days (City of Raleigh).
  10. Across eight cities, the rank correlation between the 2019 to 2021 rise in pool permit volume and the rise in median processing time was -0.19, so the cities with the biggest booms were not the ones that slowed most (PC&S analysis).
  11. Pool permit applications filed from October to December took a pooled median of 53 days to issue, compared with 42 days for January to March, across eight cities for applications filed 2019 to 2023 (PC&S analysis).
  12. New Orleans cut its median pool permit time from 38 days in January to August 2025 to 19 days in January to August 2026 (City of New Orleans).
  13. Montgomery County, Maryland says a pool permit for an adequately prepared application may take up to 17 days (Montgomery County DPS); 12.6% of 2025 permits were issued within 17 days of application (county permit data).
  14. In Orlando, Florida the median 2025 pool permit took 30 business days from application to issue, and 50.2% were issued within 30 business days (City of Orlando).
  15. Recorded fees on 2025 new residential pool permits had a median of $546 in New Orleans and $392 in Raleigh (City of New Orleans, City of Raleigh).

How we measured pool permit processing time from city records

This report counts calendar days between the application date and the issue date recorded on each new residential in-ground pool permit. It uses the same permit universe as our pool permit count report, so the two can be read together.

We started from the 14 jurisdictions in our pool construction statistics report and kept the 12 that publish both an application date and an issue date on each permit. Las Vegas publishes only an issue date (City of Las Vegas) and Fort Worth only a filing date (City of Fort Worth), so both were dropped.

The analysis covers 36,403 new residential pool permits in scope. Of these, 35,931 have a valid duration; 472 (1.3%) were excluded because the application date was missing, came after the issue date, or sat more than 730 days before issue.

Date fields and permit counts used for each jurisdiction, 2019 to August 2026
citypublisherdataseturlapplication_date_fieldapplication_field_definitionissue_date_fieldissue_years_usedpermits_in_scopepermits_with_valid_durationexcluded_no_application_dateexcluded_negativeexcluded_over_730_days
Austin, TXCity of AustinIssued Construction Permits (3syk-w9eu)https://data.austintexas.gov/d/3syk-w9euapplieddateDate on which the permit was applied; relates to the original plan review application submission where applicableissue_date2019 to Aug 20265847569701149
Los Angeles, CALA Department of Building and SafetyBuilding Permits Issued 2010 to 2019 (dyxf-7hc4) and 2020 to Present (pi9x-tg5x)https://data.lacity.org/d/pi9x-tg5xsubmitted_dateDate permit was submittedissue_date2019 to Aug 20261089810594930211
San Diego, CACity of San Diego Development ServicesDevelopment permits, approvals issued filehttps://data.sandiego.gov/datasets/development-permits-set2/PROJECT_CREATE_DATECalendar date when the Project is created in the Project Tracking SystemAPPROVAL_ISSUE_DATE2019 to Aug 202626702666004
Orlando, FLCity of OrlandoPermit Applications (ryhf-m453)https://data.cityoforlando.net/d/ryhf-m453processed_dateNo published definition; earliest workflow date on the recordissue_permit_date2019 to Aug 202626512650001
Mesa, AZCity of MesaBuilding Permits (dzpk-hxfb)https://citydata.mesaaz.gov/d/dzpk-hxfbopened_dateDate record opened (aka File Date)issued_date2019 to Aug 202643514348003
New Orleans, LACity of New OrleansPermits (rcm3-fn58)https://data.nola.gov/d/rcm3-fn58filingdateDate that the application was submitted to Safety & Permitsissuedate2019 to Aug 202615111503008
Raleigh, NCCity of RaleighBuilding Permits (ArcGIS)https://services.arcgis.com/v400IkDOw1ad7Yad/arcgis/rest/services/Building_Permits/FeatureServer/0applieddateApplied Dateissueddate2019 to Aug 2026786786000
Montgomery County, MDMontgomery County GovernmentResidential Permit (m88u-pqki)https://data.montgomerycountymd.gov/d/m88u-pqkiaddeddateThe date that the applicant applied for the permit and the information entered into the databaseissueddate2019 to Aug 2026759759000
San Antonio, TXCity of San AntonioBuilding Permits: Permits Issued (CKAN CSV)https://data.sanantonio.gov/dataset/building-permitsDATE SUBMITTEDThe date that the application was submittedDATE ISSUED2021 to Aug 202627322732000
East Baton Rouge Parish, LACity of Baton Rouge / Parish of East Baton RougeEBR Building Permits (7fq7-8j7r)https://data.brla.gov/d/7fq7-8j7rcreationdateDate permit was applied for and input into the systemissueddate2019 to 202413231323000
Nashville-Davidson, TNMetropolitan Government of Nashville and Davidson CountyBuilding Permits Issued (ArcGIS)https://services2.arcgis.com/HdTo6HJqh92wn4D8/arcgis/rest/services/Building_Permits_Issued_2/FeatureServer/0Date_EnteredDate the permit record was entered into the systemDate_Issued2024 to Aug 2026710709001
Cape Coral, FLCity of Cape CoralBuilding Permits (OpenData MapServer layer 1)https://capeims.capecoral.gov/arcgis/rest/services/OpenData/OpenData/MapServer/1applydateNo published definition beyond the field nameissuedate2025 to Aug 202621652164001

Source: city open-data portals (Austin, Los Angeles, San Diego, Orlando, Mesa, New Orleans, Raleigh, Montgomery County, San Antonio, East Baton Rouge, Nashville, Cape Coral); PC&S calculation. Download CSV

Pool permit processing time by city in 2025

The gap between the fastest and slowest jurisdictions is wide. Texas holds both ends: San Antonio issued its median pool permit in 1 day and Austin in 70 days in 2025.

Days from application to issued pool permit, 12 US jurisdictions.
Days from application to issued pool permit, 12 US jurisdictions.
Median days from application to pool permit issue, latest full year (2025; East Baton Rouge 2024), 12 US jurisdictionsCalendar days, new residential in-ground pool permits
Median days from application to pool permit issue, latest full year (2025; East Baton Rouge 2024), 12 US jurisdictionsHorizontal bar chart of median calendar days from application to permit issue for new residential pool permits in the latest full year. Austin is longest at 70 days, followed by San Diego 67, Los Angeles 61 and Cape Coral 59. Orlando is 42, Montgomery County MD 35, New Orleans and Nashville 34.5, Raleigh 30, Mesa 18, East Baton Rouge 8 (2024) and San Antonio 1.Austin: 70Austin70San Diego: 67San Diego67Los Angeles: 61Los Angeles61Cape Coral: 59Cape Coral59Orlando: 42Orlando42Montgomery County MD: 35Montgomery County MD35New Orleans: 34.5New Orleans34.5Nashville: 34.5Nashville34.5Raleigh: 30Raleigh30Mesa: 18Mesa18East Baton Rouge: 8East Baton Rouge8San Antonio: 1San Antonio1

East Baton Rouge Parish uses 2024 because its 2025 file shows a structural break.

Source: PC&S analysis of municipal open-data permit records (12 jurisdictions), pulled 2026-10-03 to 2026-10-05. Download chart data (CSV)

In 2025, Austin’s median was 70 days, San Diego’s 67, Los Angeles’s 61 and Cape Coral’s 59 (City of Austin, City of San Diego, LADBS, City of Cape Coral). Austin’s median was 3.9 times Mesa’s 18 days (City of Mesa).

The slow tail matters as much as the median. In 2025, 10% of Austin pool permits took 275 days or more, and 10% of Los Angeles permits took 274 days or more. In Mesa, the 90th percentile was 34 days.

Share of pool permits issued within 30 days of application, latest full year (2025; East Baton Rouge 2024), 12 US jurisdictionsPercent of new residential in-ground pool permits
Share of pool permits issued within 30 days of application, latest full year (2025; East Baton Rouge 2024), 12 US jurisdictionsHorizontal bar chart of the share of pool permits issued within 30 calendar days of application. San Antonio 98.3 percent, East Baton Rouge 91.2 (2024), Mesa 88.4, Raleigh 50.8, Nashville 45.2, Montgomery County MD 43.2, New Orleans 42.1, Orlando 33.2, Los Angeles 31.6, San Diego 19.8, Austin 11 and Cape Coral 8.San Antonio: 98.3%San Antonio98.3%East Baton Rouge: 91.2%East Baton Rouge91.2%Mesa: 88.4%Mesa88.4%Raleigh: 50.8%Raleigh50.8%Nashville: 45.2%Nashville45.2%Montgomery County MD: 43.2%Montgomery County MD43.2%New Orleans: 42.1%New Orleans42.1%Orlando: 33.2%Orlando33.2%Los Angeles: 31.6%Los Angeles31.6%San Diego: 19.8%San Diego19.8%Austin: 11%Austin11%Cape Coral: 8%Cape Coral8%

Source: PC&S analysis of municipal open-data permit records. Download chart data (CSV)

Pool permit processing time scorecard, latest full year (2025; East Baton Rouge Parish 2024), 12 US jurisdictions
citylatest_full_yearpermits_analysedmedian_daysp75_daysp90_dayspct_within_30_dayspct_same_daymedian_days_2019change_vs_2019_daysnote
Austin, TX2025607701342751103634
San Diego, CA20252326710516219.80166
Los Angeles, CA202510416113627431.68.21249
Cape Coral, FL20251228598713480coverage starts 2025
Orlando, FL2025259426510833.202121
Montgomery County, MD2025111356112443.201421
New Orleans, LA202515234.56210742.109.525
Nashville-Davidson, TN202524834.56610645.20coverage starts 2024
Raleigh, NC202512230498850.80.8291
Mesa, AZ202532818213488.4020-2
East Baton Rouge Parish, LA20241488142691.20.717
San Antonio, TX2025346151098.338.7coverage starts 2021

Source: PC&S analysis of municipal open-data permit records; links in the method table above. Download CSV

Did the 2021 pool boom slow pool permit processing time? Trend 2019 to 2025

Every one of the eight cities with records back to 2019 took longer to issue pool permits in 2021 than in 2019. Most have come down from their peak, but 7 of 8 were still slower in 2025 than in 2019.

Median days from application to pool permit issue, 2019 to 2025, eight US citiesCalendar days, by year of issue
Median days from application to pool permit issue, 2019 to 2025, eight US citiesLine chart of median days to issue a pool permit from 2019 to 2025 in eight cities. San Diego rises from 1 day in 2019 to 114 in 2022 and falls to 67 in 2025. Los Angeles rises from 12 to 79 in 2023 then 61 in 2025. Austin rises from 36 to 89 in 2022 then 70 in 2025. Mesa stays between 18 and 21 days throughout.03060901202019202020212022202320242025Austin, 2019: 36Austin, 2020: 46Austin, 2021: 63Austin, 2022: 89Austin, 2023: 83Austin, 2024: 73.5Austin, 2025: 70AustinLos Angeles, 2019: 12Los Angeles, 2020: 49Los Angeles, 2021: 72Los Angeles, 2022: 76Los Angeles, 2023: 79Los Angeles, 2024: 71Los Angeles, 2025: 61Los AngelesSan Diego, 2019: 1San Diego, 2020: 55San Diego, 2021: 96San Diego, 2022: 114San Diego, 2023: 110San Diego, 2024: 60.5San Diego, 2025: 67San DiegoOrlando, 2019: 21Orlando, 2020: 28Orlando, 2021: 46Orlando, 2022: 40Orlando, 2023: 47Orlando, 2024: 38.5Orlando, 2025: 42OrlandoMesa, 2019: 20Mesa, 2020: 20Mesa, 2021: 21Mesa, 2022: 21Mesa, 2023: 20Mesa, 2024: 20Mesa, 2025: 18MesaNew Orleans, 2019: 9.5New Orleans, 2020: 17New Orleans, 2021: 27New Orleans, 2022: 33New Orleans, 2023: 22New Orleans, 2024: 29New Orleans, 2025: 34.5New OrleansRaleigh, 2019: 29Raleigh, 2020: 21.5Raleigh, 2021: 32Raleigh, 2022: 23Raleigh, 2023: 26.5Raleigh, 2024: 27.5Raleigh, 2025: 30RaleighMontgomery County MD, 2019: 14Montgomery County MD, 2020: 30Montgomery County MD, 2021: 44Montgomery County MD, 2022: 41Montgomery County MD, 2023: 58.5Montgomery County MD, 2024: 45Montgomery County MD, 2025: 35Montgomery County MD

Source: PC&S analysis of municipal open-data permit records. Download chart data (CSV)

The median of the eight city medians was 17 days in 2019, 29 in 2020, 45 in 2021, 40.5 in 2022, 52.8 in 2023, 41.8 in 2024 and 38.5 in 2025 (PC&S analysis). The share issued within 30 days, again the median across the eight cities, went from 71.3% in 2019 to 31.3% in 2021 and 37.7% in 2025.

Volume explains only part of it. Our pool construction statistics report found that new pool permits in nine Sun Belt cities rose 54.0% from 2019 to 2021 and fell 47.7% from 2021 to 2025 (PC&S Research Desk). Processing times did not fall back by the same proportion.

Pool permit volume change vs change in median days to issue, eight US cities, 2019 to 2021 and 2021 to 2025
cityvolume_change_2019_2021_pctmedian_days_2019median_days_2021median_change_2019_2021_daysvolume_change_2021_2025_pctmedian_days_2025median_change_2021_2025_days
Austin, TX94.9366327-36.9707
Los Angeles, CA39.7127260-45.561-11
San Diego, CA43.119695-52.267-29
Orlando, FL52.2214625-37.942-4
Mesa, AZ22.820211-63.218-3
New Orleans, LA79.29.52717.5-43.834.57.5
Raleigh, NC195.629323-8.330-2
Montgomery County, MD63.2144430035-9

Source: PC&S analysis of municipal open-data permit records. Volume shown only as percentage change; counts are in the pool construction statistics report. Download CSV

The rank correlation between the 2019 to 2021 volume change and the change in median days was -0.19 across the eight cities. Raleigh’s volume rose 195.6% while its median rose 3 days; San Diego’s volume rose 43.1% while its median rose 95 days.

Pool permit processing time by city and year of issue, 2019 to 2025 (median, 75th and 90th percentile days, share within 30 days, share same day)
cityyearpermits_analysedmedian_daysp75_daysp90_dayspct_issued_within_30_dayspct_issued_same_day
Austin, TX2019524367014043.70
Austin, TX2020848467512333.30
Austin, TX202110186310317519.70
Austin, TX2022924891632839.50
Austin, TX20236858319436611.70
Austin, TX202456873.5154364160
Austin, TX202560770134275110
Los Angeles, CA20191397128319758.233.2
Los Angeles, CA202011834910318234.99.6
Los Angeles, CA202119727214122420.90.2
Los Angeles, CA202218537614425724.23.9
Los Angeles, CA202311967915528430.16.8
Los Angeles, CA202410827115030132.19.3
Los Angeles, CA202510416113627431.68.2
San Diego, CA20193391155981.137.8
San Diego, CA2020421558411926.85
San Diego, CA2021485961381961.90
San Diego, CA20224551141782384.60
San Diego, CA202331311018324516.60
San Diego, CA202423860.510015222.30
San Diego, CA20252326710516219.80
Orlando, FL201927321355268.90.4
Orlando, FL202037328467753.90
Orlando, FL2021417467111230.20
Orlando, FL2022392407010737.20.3
Orlando, FL2023432477111224.50
Orlando, FL202430038.5609936.70
Orlando, FL2025259426510833.20
Mesa, AZ201972820324773.80.3
Mesa, AZ202089920295175.90.3
Mesa, AZ202189321305675.40.6
Mesa, AZ202252821376469.70.4
Mesa, AZ202338320305476.20
Mesa, AZ202434820264779.90
Mesa, AZ202532818213488.40
New Orleans, LA20191549.5214886.46.5
New Orleans, LA202019217295177.10
New Orleans, LA2021276276110655.40
New Orleans, LA2022231336210348.10
New Orleans, LA20232032247104640
New Orleans, LA202415929438052.80
New Orleans, LA202515234.56210742.10
Raleigh, NC20194529529657.80
Raleigh, NC20209421.5395563.80
Raleigh, NC2021133325810549.60.8
Raleigh, NC202210623528661.30.9
Raleigh, NC20239626.5397259.40
Raleigh, NC20249027.5578053.30
Raleigh, NC202512230498850.80.8
Montgomery County, MD20196814285176.513.2
Montgomery County, MD20209130466452.71.1
Montgomery County, MD2021111448012532.40
Montgomery County, MD2022102418720339.20
Montgomery County, MD202311458.58913025.40
Montgomery County, MD2024954510323134.70
Montgomery County, MD2025111356112443.20
San Antonio, TX20217103112293.723.7
San Antonio, TX2022595484787.120.8
San Antonio, TX2023479372291.630.3
San Antonio, TX202440127159630.7
San Antonio, TX2025346151098.338.7
East Baton Rouge Parish, LA2019153161396.736.6
East Baton Rouge Parish, LA20202645132195.517
East Baton Rouge Parish, LA202129812213387.91.3
East Baton Rouge Parish, LA202226615284377.40
East Baton Rouge Parish, LA20231948193489.20
East Baton Rouge Parish, LA20241488142691.20.7
Nashville-Davidson, TN2024229346411446.70.9
Nashville-Davidson, TN202524834.56610645.20
Cape Coral, FL20251228598713480

Source: PC&S analysis of municipal open-data permit records. Download CSV

The 2020 counter closures and the end of same-day pool permits in Los Angeles and San Diego

The steepest change in the data is a step, not a slope. In Los Angeles and San Diego, roughly a third of pool permits were issued the day of application until early 2020; by the end of 2020 almost none were.

Over-the-counter permitting gave way to drop-off and online submittal in 2020.
Over-the-counter permitting gave way to drop-off and online submittal in 2020.
Share of pool permits issued on the day of application, by quarter, Los Angeles and San Diego, 2019 to 2021Percent of new residential pool permits issued in the quarter
Share of pool permits issued on the day of application, by quarter, Los Angeles and San Diego, 2019 to 2021Line chart by quarter from 2019 Q1 to 2021 Q4. Same-day issuance of pool permits held between 26.6 and 49.4 percent in the two cities through 2020 Q1, then fell to 10.1 percent in Los Angeles and 0 percent in San Diego in 2020 Q2, and stayed at or near zero through 2021.0%12.5%25%37.5%50%2019Q12019Q22019Q32019Q42020Q12020Q22020Q32020Q42021Q12021Q22021Q32021Q4Los Angeles same-day %, 2019Q1: 31.8%Los Angeles same-day %, 2019Q2: 34.5%Los Angeles same-day %, 2019Q3: 35.7%Los Angeles same-day %, 2019Q4: 30.7%Los Angeles same-day %, 2020Q1: 32.2%Los Angeles same-day %, 2020Q2: 10.1%Los Angeles same-day %, 2020Q3: 1.8%Los Angeles same-day %, 2020Q4: 0%Los Angeles same-day %, 2021Q1: 0.2%Los Angeles same-day %, 2021Q2: 0%Los Angeles same-day %, 2021Q3: 0.2%Los Angeles same-day %, 2021Q4: 0.2%Los Angeles same-day %San Diego same-day %, 2019Q1: 37.1%San Diego same-day %, 2019Q2: 26.6%San Diego same-day %, 2019Q3: 49.4%San Diego same-day %, 2019Q4: 39.7%San Diego same-day %, 2020Q1: 29.2%San Diego same-day %, 2020Q2: 0%San Diego same-day %, 2020Q3: 0%San Diego same-day %, 2020Q4: 0%San Diego same-day %, 2021Q1: 0%San Diego same-day %, 2021Q2: 0%San Diego same-day %, 2021Q3: 0%San Diego same-day %, 2021Q4: 0%San Diego same-day %

LADBS modified counter operations in March 2020; San Diego moved all new projects to online submittal from 4 May 2020.

Source: PC&S analysis of LADBS and City of San Diego permit records. Download chart data (CSV)

In Los Angeles, 32.2% of pool permits issued in Q1 2020 were issued the day of application; in Q4 2020 the share was 0.0% and the median was 64 days, up from 6 days (LADBS). LADBS says it modified public counter operations in March 2020 and that drop-off screening “created inefficiencies” and “a prolonged response” (LADBS).

In San Diego, the same-day share fell from 29.2% in Q1 2020 to 0.0% in Q2 2020, and the median went from 5 days to 53 days (City of San Diego). From 4 May 2020 the city began accepting online submittals for all new projects (Times of San Diego).

Does the month you apply change pool permit processing time?

Most months sit close to a city’s typical time. The exception is the year-end: applications filed in November and December take longer, consistent with holiday closures falling inside the review window.

Pool permit processing time by month of application, eight US cities, applications filed 2019 to 2023Index: 100 = each city's typical median; median across eight cities
Pool permit processing time by month of application, eight US cities, applications filed 2019 to 2023Vertical bar chart of an index of median processing time by month of application. January is 91, February 93, March to October between 96 and 101, November 106 and December 117, meaning December applications took about 17 percent longer than a typical month.0306090120Jan: 91JanFeb: 93FebMar: 101MarApr: 98AprMay: 99MayJun: 98JunJul: 96JulAug: 97AugSep: 98SepOct: 101OctNov: 106NovDec: 117Dec

Source: PC&S analysis of municipal open-data permit records. Download chart data (CSV)

For 21,270 applications filed 2019 to 2023 in eight cities, the month index was 91 for January, 106 for November and 117 for December, where 100 is each city’s typical median (PC&S analysis). Pooled, October to December applications took a median of 53 days to issue, against 42 days for January to March and 43 days for both April to June and July to September.

Median days from application to pool permit issue by month of application, eight US cities, applications filed 2019 to 2023
application_monthindex_median_city_100pooled_median_days_8_citiesapplications_analysedAustin_median_daysLos Angeles_median_daysSan Diego_median_daysOrlando_median_daysMesa_median_daysNew Orleans_median_daysRaleigh_median_daysMontgomery County MD_median_days
Jan914116415857.51002721212329.5
Feb9342157265.55863342023.52229
Mar10142189064.554.589.5432022.52644.5
Apr9839.51652665078.53219242928
May994418926461714820251942.5
Jun98462009636163362021.54540.5
Jul9640179368.560782920172530.5
Aug97451838615871372018.52852
Sep9846185658646539.520212737
Oct1014919097473763620212342
Nov1065415857064903621254942
Dec1175516337177.5734821283049

Source: PC&S analysis of municipal open-data permit records. Download CSV

Pool permit processing time in 2026 so far: January to August vs 2025

Comparing the same eight months in both years, more jurisdictions got faster than slower. The largest improvements came in New Orleans, Cape Coral and Nashville.

Change in median days to issue a pool permit, January to August 2026 vs January to August 2025, 11 US jurisdictionsDays; negative = faster in 2026
Change in median days to issue a pool permit, January to August 2026 vs January to August 2025, 11 US jurisdictionsHorizontal bar chart of the change in median days to issue a pool permit between January to August 2025 and January to August 2026. New Orleans fell 19 days, Cape Coral 18, Nashville 14, Austin 8, Raleigh 7.5 and Montgomery County 2.5. San Antonio was unchanged. Orlando rose 1 day, Mesa 2, Los Angeles 3.5 and San Diego 13.New Orleans: -19New Orleans-19Cape Coral: -18Cape Coral-18Nashville: -14Nashville-14Austin: -8Austin-8Raleigh: -7.5Raleigh-7.5Montgomery County MD: -2.5Montgomery County MD-2.5San Antonio: 0San Antonio0Orlando: 1Orlando1Mesa: 2Mesa2Los Angeles: 3.5Los Angeles3.5San Diego: 13San Diego13

Source: PC&S analysis of municipal open-data permit records. Download chart data (CSV)

From January to August 2026, the median fell from 38 to 19 days in New Orleans (City of New Orleans), 58 to 40 days in Cape Coral (City of Cape Coral) and 42 to 28 days in Nashville (Metro Nashville). It rose from 75 to 88 days in San Diego (City of San Diego) and from 61 to 64.5 days in Los Angeles (LADBS).

Pool permit processing time, January to August 2026 vs January to August 2025, 11 US jurisdictions
citypermits_jan_aug_2025median_days_jan_aug_2025permits_jan_aug_2026median_days_jan_aug_2026change_dayspct_within_30_jan_aug_2025pct_within_30_jan_aug_2026
New Orleans, LA1013812019-1931.771.7
Cape Coral, FL8115880740-188.429.2
Nashville-Davidson, TN1614219528-144154.4
Austin, TX4097046662-81219.3
Raleigh, NC81319223.5-7.548.164.1
Montgomery County, MD7637.55935-2.538.239
San Antonio, TX2451175109897.7
Orlando, FL1814118842134.326.1
Mesa, AZ2331820720288.878.3
Los Angeles, CA6906177664.53.532.926.5
San Diego, CA14975157881322.88.3

Source: PC&S analysis of municipal open-data permit records. Download CSV

Published permit deadlines compared with observed pool permit processing time

Florida and Texas set statutory clocks for building permit decisions, and some cities publish their own targets. Our measure is not a compliance test, because those clocks start at a complete application and pause for corrections, but the comparison shows how far typical owner waits sit from the published numbers.

  • Florida: a local government must approve, approve with conditions or deny a complete and sufficient residential or accessory-structure application under 7,500 square feet within 30 business days, or reduce the permit fee by 10% for each business day late unless an exception applies (Florida Statutes s. 553.792). In 2025, Orlando’s median was 30 business days and Cape Coral’s 42 business days from application to issue; 50.2% and 33.1% respectively were issued within 30 business days (PC&S analysis).
  • Texas: by the 45th day after an application, a municipality must grant or deny the permit, give written reasons for the delay, or agree a deadline with the applicant (Texas Local Government Code s. 214.904). In 2025, 24.1% of Austin and 98.6% of San Antonio pool permits were issued within 45 calendar days (PC&S analysis).
  • Montgomery County, Maryland: up to 17 days to issue a pool permit for an adequately prepared application (Montgomery County DPS). The 2025 median was 35 days, 18 days longer, and 12.6% of permits were issued within 17 days (PC&S analysis).
  • Mesa, Arizona: written comments or approval within 10 working days, counting Monday to Thursday (City of Mesa). The 2025 median from application to issue was 18 calendar days (PC&S analysis).

Why pool permits take longer in some cities

The data point to process design more than to pool demand. Cities where pool permits move through counter or express review show short medians; cities where most pool permits enter full plan review with correction cycles show long ones.

  • Plan review cycles: LADBS says regular plan check plans are assigned within a few days and returned “within weeks depending on workload”, and an expedited review costs 50% more of the plan check fee (LADBS).
  • Repeat designs: Montgomery County says permits for the same model pool built in other locations may be issued without building plan review (Montgomery County DPS). Florida sets a 12-business-day clock for site-specific permits issued under a master building permit (Florida Statutes s. 553.792).
  • Incomplete applications: Florida requires local governments to tell applicants within 5 business days what is missing (Florida Statutes s. 553.792); Austin deems an application abandoned if it is not pursued or issued within 180 days of filing (City of Austin).
  • Timing: applications filed in December took 17% longer than a typical month across eight cities, 2019 to 2023 (PC&S analysis).
Inspections follow issuance; most cities require the permit before any excavation.
Inspections follow issuance; most cities require the permit before any excavation.

For barrier rules that pool plans must show, see pool fence laws by state. For who may pull a pool permit, see pool contractor license requirements.

Measures we built from the data

Median days to issue by city, latest full year

How long does a pool permit take in each city?

Formulamedian(issue date minus application date) over valid new residential in-ground pool permits issued in the year

Inputs: fact rows #38, #362, #206 and the other city rows for 2025 (2024 for East Baton Rouge)

Medians in 2025 ranged from 1 day in San Antonio to 70 days in Austin; 7 of 12 jurisdictions were at 35 days or less and 4 of 12 above 55 days.

Limitations: Application date fields differ by city; durations above 730 days or below 0 excluded.

Trend 2019 to 2025 and the boom

Did the 2021 boom slow pool permits?

Formulamedian of the eight city medians per year; Spearman rank correlation of city-level volume change and median-days change, 2019 to 2021

Inputs: derived rows D-series "Median of eight city medians" (2019 to 2025) and the Spearman row; volume counts in facts.csv (vol rows)

The median of city medians rose from 17 days (2019) to 45 (2021) and a high of 52.8 (2023), then 38.5 (2025). All 8 cities were slower in 2021 than 2019, but the rank correlation with volume growth was -0.19.

Limitations: Eight cities only; 2020 also brought counter closures, so volume and process changes overlap.

Share issued within 30 days

How likely is a pool permit inside a month?

Formulapermits with 0 to 30 days / all valid permits x 100, per city and year; median across eight cities

Inputs: fact rows "Share of pool permits issued within 30 calendar days" per city and year

Median across eight cities: 71.3% in 2019, 31.3% in 2021, 37.7% in 2025. In 2025 the range ran from 8% in Cape Coral to 98.3% in San Antonio.

Limitations: Calendar days; weekends and holidays included.

Month-of-application effect

Does applying in a particular month slow a pool permit?

Formulafor each city: median days for applications in month m / median days for all months x 100; then median across eight cities

Inputs: fact rows "Median calendar days … applications filed in month m, 2019 to 2023" and city base medians

Index 91 for January, 117 for December and 106 for November; pooled medians 53 days for October to December vs 42 days for January to March.

Limitations: Applications 2019 to 2023 only; includes the 2020 to 2021 disruption.

Same-day issuance before and after 2020

How did the 2020 counter changes show up in permit dates?

Formulapermits with 0 days / all valid permits x 100, by quarter of issue

Inputs: fact rows "Share of pool permits issued on the day of application, permits issued in quarter" for Los Angeles and San Diego

Los Angeles: 32.2% (Q1 2020) to 0.0% (Q4 2020). San Diego: 29.2% (Q1 2020) to 0.0% (Q2 2020).

Limitations: Cause cannot be isolated from the concurrent rise in applications.

Observed times vs published targets

How do owner waits compare with statutory or published deadlines?

Formulashare of 2025 permits with duration at or below the published figure (calendar or business days as stated)

Inputs: fact rows #755, #756, #757, #758, #759, #762, #767, #778

Montgomery County 12.6% within 17 days; Austin 24.1% and San Antonio 98.6% within 45 days; Orlando 50.2% and Cape Coral 33.1% within 30 business days.

Limitations: Statutory clocks start at a complete application and pause for corrections; this is not a compliance measure. Business days exclude weekends but not holidays.

Download the calculation sheet (CSV)

Latest data in this edition

  • First edition. Permit records pulled 3 to 5 October 2026; complete through August 2026 in all 11 jurisdictions with 2026 data.
  • January to August 2026: 6 of 11 jurisdictions issued pool permits faster than in January to August 2025; San Diego (+13 days) slowed most.
  • Cape Coral, Florida published permit layer starts in January 2025; its 2025 median was 59 days, falling to 40 days in January to August 2026.

Quick answers

How long does it take to get a pool permit?

In 2025, the median new residential pool permit was issued 1 day after application in San Antonio, 18 days in Mesa, 30 in Raleigh, 35 in Montgomery County, Maryland, 42 in Orlando, 61 in Los Angeles and 70 in Austin (PC&S analysis of city permit records). The median across eight long-run cities was 38.5 days.

Why is my pool permit taking so long?

Most of the wait in slow cities is plan review and correction cycles: LADBS says regular plan check plans are returned “within weeks depending on workload” (LADBS). Our clock also counts applicant response time. Timing plays a part: December applications took 17% longer than a typical month across eight cities, 2019 to 2023.

Do you need a permit to build a pool?

In the cities checked, yes for in-ground pools. Mesa lists constructing an in-ground swimming pool as work that needs a permit (City of Mesa). San Antonio exempts only prefabricated pools entirely above ground that are under 24 inches deep and hold no more than 5,000 gallons (City of San Antonio).

Can you start digging before the permit is issued?

Nashville says that once all required signoffs are in, you can pay for the permit and begin construction (Metro Nashville); Orlando requires an engineering pre-walk inspection before work begins (City of Orlando). In Los Angeles, work needing a permit after the fact carries an investigation fee of double the permit fee, never less than $400 (LADBS). Not legal advice.

How much does a pool permit cost?

Fees depend on the city and project value. Recorded fees on 2025 new residential pool permits had a median of $546 in New Orleans and $392 in Raleigh (City of New Orleans, City of Raleigh). Mesa bases fees on estimated construction cost (City of Mesa).

Questions and answers

Which US city issues pool permits fastest?

Of the 12 jurisdictions analysed, San Antonio, Texas had the shortest 2025 median at 1 day from application to issue, with 38.7% issued the same day (City of San Antonio).

Which city has the longest pool permit processing time?

Austin, Texas had the longest 2025 median at 70 days, and 10% of its pool permits took 275 days or more (City of Austin).

What share of pool permits are issued within 30 days?

Across eight cities tracked since 2019, the median share issued within 30 days was 37.7% in 2025, down from 71.3% in 2019 (PC&S analysis of city permit records).

Are pool permits faster in 2026 than in 2025?

In 6 of 11 jurisdictions, yes: comparing January to August, the median fell in New Orleans (38 to 19 days), Cape Coral (58 to 40) and Nashville (42 to 28), while San Diego rose from 75 to 88 days (PC&S analysis).

Did the pandemic slow pool permits?

In Los Angeles the median pool permit went from 6 days in Q1 2020 to 64 days in Q4 2020, as same-day issuance fell from 32.2% to 0.0% (LADBS). LADBS modified its public counters in March 2020 (LADBS).

Is it worse to apply for a pool permit in December?

Across eight cities, applications filed in December took 17% longer than a typical month (index 117), and October to December applications had a pooled median of 53 days vs 42 for January to March, 2019 to 2023 (PC&S analysis).

What is the Florida deadline for a residential permit decision?

Florida requires a decision within 30 business days of a complete and sufficient application for residential and accessory-structure permits under 7,500 square feet using the local plans reviewer, with a 10% fee reduction per business day late unless an exception applies (Florida Statutes s. 553.792). Not legal advice.

What does Texas law say about building permit timing?

By the 45th day after an application, a Texas municipality must grant or deny the permit, give written reasons for the delay, or agree a deadline with the applicant (Texas Local Government Code s. 214.904). In 2025, 24.1% of Austin pool permits were issued within 45 calendar days. Not legal advice.

How long does Montgomery County, Maryland take to issue a pool permit?

The county says up to 17 days for adequately prepared applications (Montgomery County DPS); the recorded 2025 median from application to issue was 35 days (county permit data).

How was pool permit processing time measured?

We subtracted the recorded application date from the issue date for 35,931 new residential in-ground pool permits in 12 jurisdictions, 2019 to August 2026, after excluding 472 records with missing, negative or over-730-day durations (PC&S analysis).

Data, citation and press kit

Figures ready to quote

  • In 2025, the median new residential pool permit in Austin, Texas took 70 days from application to issue, compared with 1 day in San Antonio. (City of Austin)
  • Across eight US cities, the median of city medians for pool permit processing time rose from 17 days in 2019 to 38.5 days in 2025. (LA Department of Building and Safety)
  • The median share of pool permits issued within 30 days across eight US cities fell from 71.3% in 2019 to 37.7% in 2025. (City of San Diego Development Services)
  • In Los Angeles, the share of pool permits issued on the day of application fell from 32.2% in Q1 2020 to 0.0% in Q4 2020. (LA Department of Building and Safety)
  • Pool permit applications filed in December took 17% longer than a typical month to be issued across eight US cities, 2019 to 2023. (City of Orlando)
  • From January to August 2026, 6 of 11 US jurisdictions issued pool permits faster than in the same months of 2025. (City of New Orleans)

If you cite only a few sources

Summary for editors

A new PC&S Research Desk analysis of 35,931 permit records from 12 US cities and counties measures how long homeowners wait for a new in-ground pool permit. In 2025, the median permit took 1 day from application to issue in San Antonio, 18 days in Mesa, 42 in Orlando, 61 in Los Angeles and 70 in Austin. Across eight cities with records back to 2019, the median of city medians rose from 17 days in 2019 to 38.5 days in 2025, and the share issued within 30 days fell from 71.3% to 37.7%. The biggest change came in 2020: same-day issuance in Los Angeles fell from 32.2% to 0.0% within a year as counters closed. Bigger permit booms did not predict bigger slowdowns. Applications filed in December took 17% longer than a typical month. From January to August 2026, 6 of 11 jurisdictions were faster than a year earlier, led by New Orleans. All data and methods are downloadable.

Headlines the data supports

  • Pool permits take 70 days in Austin and 1 day in San Antonio, city records show
  • Pool permit waits more than doubled in eight US cities between 2019 and 2025
  • Same-day pool permits vanished in Los Angeles and San Diego in 2020
  • Applying for a pool permit in December adds 17% to the wait, permit data show
  • Pool permits are getting faster in 6 of 11 US jurisdictions in 2026

How to cite this report

Pool Construction & Service. "Pool Permit Processing Time: Days From Application to Issue in 12 US Cities, 2019 to 2026." PC&S Research Desk, October 5, 2026. https://poolconstructionandservice.com/research/pool-permit-processing-time/

Reuse

The data tables and charts in this report are licensed under CC BY 4.0. Reuse them with this attribution: “Source: Pool Construction & Service (poolconstructionandservice.com), Pool Permit Processing Time: Days From Application to Issue in 12 US Cities, 2019 to 2026.” Figures from third-party sources remain subject to their publishers’ terms.

Download the data

How we graded sources

Tier 1: primary and government sources (25)

Tier 2: trade bodies, public companies, market research (2)

Tier 3: journalism and expert commentary (1)

Sources

  1. City of Austin. Issued Construction Permits (3syk-w9eu). Accessed 2026-10-03.
  2. LA Department of Building and Safety. Building and Safety: Building Permits Issued from 2020 to Present (pi9x-tg5x). Accessed 2026-10-05.
  3. LA Department of Building and Safety. Building and Safety: Building Permits Issued Between 2010 and 2019 (dyxf-7hc4). Accessed 2026-10-05.
  4. City of San Diego Development Services. Development Permits (approvals issued file and data dictionary). Accessed 2026-10-05.
  5. City of Orlando. Permit Applications (ryhf-m453). Accessed 2026-10-05.
  6. City of Mesa. Building Permits (dzpk-hxfb). Accessed 2026-10-03.
  7. City of New Orleans. Permits (rcm3-fn58). Accessed 2026-10-03.
  8. City of Raleigh. Building Permits (ArcGIS feature service). Accessed 2026-10-03.
  9. Montgomery County Government, Maryland. Residential Permit (m88u-pqki). Accessed 2026-10-03.
  10. City of San Antonio. Building Permits: Permits Issued and data dictionary. Accessed 2026-10-05.
  11. City of Baton Rouge / Parish of East Baton Rouge. EBR Building Permits (7fq7-8j7r). Accessed 2026-10-03.
  12. Metropolitan Government of Nashville and Davidson County. Building Permits Issued (ArcGIS feature service). Accessed 2026-10-03.
  13. City of Cape Coral. Building Permits (OpenData MapServer layer 1). Accessed 2026-10-03.
  14. The Florida Senate. Florida Statutes s. 553.792, Building permit application to local government (2025). Accessed 2026-10-05.
  15. FindLaw (reproducing the Texas statute). Texas Local Government Code s. 214.904, Time for Issuance of Municipal Building Permit (text current as of 1 January 2026). Accessed 2026-10-05.
  16. LA Department of Building and Safety. New LADBS Submittal and Verifications Procedures. Accessed 2026-10-05.
  17. LA Department of Building and Safety. Regular Plan Check. Accessed 2026-10-05.
  18. LA Department of Building and Safety. Code Enforcement Bureau Fees Explained. Accessed 2026-10-05.
  19. Times of San Diego. City of San Diego Pivots to Electronic Permitting During COVID-19 Pandemic (27 April 2020). Accessed 2026-10-05.
  20. City of Mesa. Residential Construction (building permit and plan review). Accessed 2026-10-05.
  21. Montgomery County Department of Permitting Services. Residential Swimming Pool. Accessed 2026-10-05.
  22. Metro Nashville Codes and Building Safety. Building Permits Central: Residential Pool Permitting Instructions. Accessed 2026-10-05.
  23. City of Orlando. Residential Swimming Pool and Spa Checklist. Accessed 2026-10-05.
  24. City of San Antonio Development Services. Residential Swimming Pool or Spa Permit Application. Accessed 2026-10-05.
  25. City of Austin. International Swimming Pool and Spa Code: proposed adoption and local amendments. Accessed 2026-10-05.
  26. City of Las Vegas. Building Permits (OpenData_Building_Permits_, checked for date fields; not used). Accessed 2026-10-03.
  27. City of Fort Worth. CFW Open Data Development Permits (checked for date fields; not used). Accessed 2026-10-03.
  28. PC&S Research Desk. Pool Construction Statistics: New Pool Permits in 14 US Markets, 2015 to 2026. Accessed 2026-10-05.